UPDATE ON BUILD PROGRESS FEB 13

3 February 2013 / Project Thorney / Build Works

Another two weeks since the last building development blog post and we’ve made significant progress. Our foundations are laid for the boiler room and the new internal rooms have their framework established.

The old Annexe becomes the new Grasmere Bunkhouse

The new corridor is being formed, door openings to rooms and shower block.
corridor door openings formed

Showing the full length of the corridor. Four new 4 person bunk rooms.
corridor room openings formed

2 extra toilets. OK you need to use your imagination a bit.
rooms taking shape

This will be the new shower block entrance with 3 showers and a further toilet.
establishing shower room door

A new ceiling for the shower room has had to built, extra storage space above.
new shower room ceiling

The old door (green) is about to go. The new opening will now give access to from the western side of the Bunkhouse.
new shower room external access

Blocks ready for the new plant room build.
blocks for construction delivered

First concrete delivery.
Concrete delivery number 1

Our technical solution to pouring the concrete down a 3m drop.
Concrete pouring 3

It’s all flowing smoothly, and the rig is still standing despite the weight.
Concrete pouring 1

Getting a good even distribution. Our biomass boiler plant room will be standing here soon.
Concrete pouring 2

Almost done and no snow today.
The new foundations

A bit of spare cement will do niceley to help along the new disabled access to the front door and reception.
New disabled access